Hindustan Zinc Approves ₹80,000 Crore Growth Program
VEDL - Key Highlights - Massive Capacity Expansion: Refined metal production capacity will grow by ~1 MTPA (from 1.1 MTPA to ~2.02 MTPA), with Zinc smelting reaching 1,611 KTPA and Lead smelting hitting 410 KTPA. Silver Output Nearly Doubles: Silver refining capacity will expand from 800 TPA to 1,500 TPA via a new 700 TPA silver refinery. ₹80,000 Crore Capex: Financed through a mix of internal accruals and debt, the investment covers new smelters, refineries, mining/milling expansion, and related infrastructure. Phased Execution Roadmap:Phase 1 (by 2QFY29): Commissioning of an enhanced 265 KTPA integrated zinc smelter at Debari (upgraded from the earlier 250 KTPA plan within the same budget), taking total refined capacity toward 1.4 MTPA (net of an 88 KTPA Debari cell house discontinuation). Phase 2 (3–5 Years): Commissioning of a new 500 KTPA zinc smelter, a 200 KTPA lead smelter, and the 700 TPA silver refinery. Mine & Tailings Scaling: Total ore production capacity across Rajasthan mines will expand from 19.3 MTPA to 35.0 MTPA. Additionally, an extra ₹3,823 crore is earmarked for India's first 10 MTPA tailings reprocessing plant at Rampura Agucha to supply smelter feed. - Strategic Rationale & Macro Drivers - Operating at an existing capacity utilization of roughly 92% (FY26), Hindustan Zinc is positioning itself to capture surging domestic demand. India's Infrastructure & Steel Boom: India's crude steel production capacity is projected to climb from 205 MnT in FY25 to 300 MnT by FY30, alongside record government capital expenditure (budgeted at ₹12.2 lakh crore or ~4.4% of GDP for FY27). Doubling Domestic Zinc Demand: Driven by construction, automotive growth, manufacturing, and renewable energy additions, Indian zinc demand is projected to double within the next 5 to 10 years. Read Disclaimer/Disclosure : click to link in Bio :