ACME Solar Holdings Commissions Phase III of 11.429 MW BESS Project in Rajasthan

ACMESOLAR
ACME Solar Holdings has successfully commissioned the third phase of its Battery Energy Storage System project in Rajasthan, adding 11.429 MW / 51.354 MWh capacity with Commercial Operation Date of March 31, 2026. The milestone brings the total commissioned capacity to 107.143 MW / 481.440 MWh out of the project's full capacity of 250 MW / 1103.392 MWh, demonstrating continued progress in the company's renewable energy infrastructure development.