A) Capex & Commissioning Guidance
a) FY25 Capex: Rs 7,800 crore
b) FY26 Capex Target: Rs 8,300 crore
c) FY27 Capex Target: Rs 12,000 crore
B) Growth & Strategic Developments
a) Total operational capacity: 2,786.5 MW (13 projects + 2 transmission lines)
b) Projects under construction: 4,601 MW (4 hydro, 1 thermal, 11 solar)
c) PM Surya Ghar Muft Bijli Yojana:
d) SJVN selected as implementing agency
e) Also responsible for rooftop solar on govt. buildings (18 ministries)
f) REIA (Renewable Energy Implementing Agency) status**:
g) 18.6 GW tenders floated (vs target of 20.8 GW)
h)13.7 GW LoAs issued
i) 5.2 GW PPAs signed (3 GW in FY25, 2.2 GW in FY24)
j) Rs 7 /MWh trading margin → Projected Rs 200 Cr recurring EBITDA by FY27
C) Storage Projects
a) In early development in Maharashtra, Chhattisgarh, Rajasthan, Mizoram
b) DPR completion expected by mid-2027
c) Construction likely from late FY27, with 4–5 year build cycle