Commercial Operation Update - NTPC Ltd

Code BSE: 532555 NSE:

NTPC
NTPC Ltd anounced second & last part capacity of 52 MW out of 245 MW capacity at Plot-3 of NTPC's Nokh Solar PV Project (3x245MW), Rajasthan, is declared on Commercial Operation w.e.f. 00:00 ***** 22.06.2025. The first part capacity of 193 MW has already been declared on commercial operation w.e.f. 00:00 Hrs. of 09.06.2025. With this, the total standalone and group commercial capacity has now become 60,318 MW & 81,420 MW respectively. Total standalone and group installed capacity has now become 60,978 MW & 82,080 MW respectively

#WatchOutFor
NTPC22062025.pdf