Commissioning, the fourth part capacity of 37.95 MW out of 300 MW - NTPC Green Energy Ltd
Code BSE: 544289 NSE:
NTPCGREEN
We wish to inform you that consequent upon successful commissioning, the fourth part capacity of 37.95 MW out of 300 MW Khavda Solar Energy Project at Khavda, Bhuj, Gujarat of NTPC Renewable Energy Limited, a wholly owned subsidiary of NTPC Green Energy Limited, under 450 MW Hybrid Tranche V Project is declared on Commercial Operation w.e.f. 00:00 Hrs of 19.10.2025.
The first part capacity of 142.2 MW, second part capacity of 32.8 MW and third part capacity of 49.125 MW has already been declared on commercial operation w.e.f. 28.06.2025, 30.06.2025 and 22.08.2025 respectively. The total capacity declared on commercial operation is 262.075 MW.
The current commercial capacity of NTPC Green Energy Limited Group stands at 7515.725 MW. With the addition of this capacity, the total installed capacity of the NGEL Group will increase to 7553.675 MW.